• IfcTaskTimeRecurring


    IfcTaskTimeRecurring

    实体定义

    IfcTaskTimeRecurtive是IfcTaskTime的重复实例,用于处理定期计划或重复的任务。

    IFC4中的新实体。

    Attribute inheritance

    #AttributeTypeCardinalityDescriptionC
    IfcSchedulingTime
    1 Name IfcLabel [0:1] Optional name for the time definition. X
    2 DataOrigin IfcDataOriginEnum [0:1] Specifies the origin of the scheduling time entity. It currently differentiates between predicted, simulated, measured, and user defined values. X
    3 UserDefinedDataOrigin IfcLabel [0:1] Value of the data origin if DataOrigin attribute is USERDEFINED. X
    IfcTaskTime
    4 DurationType IfcTaskDurationEnum [0:1] Enables to specify the type of duration values for ScheduleDurationActualDuration and RemainingTime. The duration type is either work time or elapsed time. X
    5 ScheduleDuration IfcDuration [0:1] The amount of time which is scheduled for completion of a task. The value might be measured or somehow calculated, which is defined by ScheduleDataOrigin. The value is either given as elapsed time or work time, which is defined by DurationType.
    NOTE  Scheduled Duration may be calculated as the time from scheduled start date to scheduled finish date.
    X
    6 ScheduleStart IfcDateTime [0:1] The date on which a task is scheduled to be started. The value might be measured or somehow calculated, which is defined by ScheduleDataOrigin.
    NOTE  The scheduled start date must be greater than or equal to the earliest start date.
    X
    7 ScheduleFinish IfcDateTime [0:1] The date on which a task is scheduled to be finished. The value might be measured or somehow calculated, which is defined by ScheduleDataOrigin.
    NOTE  The scheduled finish date must be greater than or equal to the earliest finish date.
    X
    8 EarlyStart IfcDateTime [0:1] The earliest date on which a task can be started. It is a calculated value. X
    9 EarlyFinish IfcDateTime [0:1] The earliest date on which a task can be finished. It is a calculated value. X
    10 LateStart IfcDateTime [0:1] The latest date on which a task can be started. It is a calculated value. X
    11 LateFinish IfcDateTime [0:1] The latest date on which a task can be finished. It is a calculated value. X
    12 FreeFloat IfcDuration [0:1] The amount of time during which the start or finish of a task may be varied without any effect on the overall programme of work. It is a calculated elapsed time value. X
    13 TotalFloat IfcDuration [0:1] The difference between the duration available to carry out a task and the scheduled duration of the task. It is a calculated elapsed time value.
    NOTE  Total Float time may be calculated as being the difference between the scheduled duration of a task and the available duration from earliest start to latest finish. Float time may be either positive, zero or negative. Where it is zero or negative, the task becomes critical.
    X
    14 IsCritical IfcBoolean [0:1] A flag which identifies whether a scheduled task is a critical item within the programme.
    NOTE  A task becomes critical when the float time becomes zero or negative.
    X
    15 StatusTime IfcDateTime [0:1] The date or time at which the status of the tasks within the schedule is analyzed. X
    16 ActualDuration IfcDuration [0:1] The actual duration of the task. It is a measured value. The value is either given as elapsed time or work time, which is defined by DurationType. X
    17 ActualStart IfcDateTime [0:1] The date on which a task is actually started. It is a measured value.
    NOTE  The scheduled start date must be greater than or equal to the earliest start date. No constraint is applied to the actual start date with respect to the scheduled start date since a task may be started earlier than had originally been scheduled if circumstances allow.
    X
    18 ActualFinish IfcDateTime [0:1] The date on which a task is actually finished. X
    19 RemainingTime IfcDuration [0:1] The amount of time remaining to complete a task. It is a predicted value. The value is either given as elapsed time or work time, which is defined by DurationType.
    NOTE  The time remaining in which to complete a task may be determined both for tasks which have not yet started and those which have. Remaining time for a task not yet started has the same value as the scheduled duration. For a task already started, remaining time is calculated as the difference between the scheduled finish and the point of analysis.
    X
    20 Completion IfcPositiveRatioMeasure [0:1] The extent of completion expressed as a ratio or percentage. It is a measured value. X
    IfcTaskTimeRecurring
    21 Recurrence IfcRecurrencePattern [1:1]   X
     
     

    EXPRESS Specification

    ENTITY IfcTaskTimeRecurring
     SUBTYPE OF (IfcTaskTime);
      Recurrence : IfcRecurrencePattern;
    END_ENTITY;

    #################################

  • 相关阅读:
    梯度消失和梯度爆炸
    BN的作用与使用过程
    百面机器学习笔记(二)
    正则表达式
    CSS Sprite
    事件绑定
    拖拽
    oncontextmenu
    鼠标跟随
    鼠标事件
  • 原文地址:https://www.cnblogs.com/herd/p/16511853.html
Copyright © 2020-2023  润新知